Neat Solutions (PVT) ltd has taken over land reclamation work at Prima facility In Trincomalee and currently handling maintenance work until the handover after completion.
Total area cleared after excavation – 7.5 acre
Total area filled – 8.5 acre
Total area cleared and filled – 20 acre
Additional road construction work in project 3- Land Reclamation at Trincomalee was commenced on 17.02.2016 to 17.03.2016. The cost of this project was 3 million. It consisted of site mobilization, demolition of existing parts of the road, constructing new part of the road and demobilization.